How to Calculate How Much Soil Needs to Be Excavated

How to Calculate How Much Soil Needs to Be Excavated

How to Calculate How Much Soil Needs to Be Excavated

How to Calculate How Much Soil Needs to Be Excavated

Whether you’re digging a swimming pool, preparing a house site, excavating a trench or carrying out bulk earthworks, one of the first things you need to work out is how much material needs to be removed.

Knowing how to calculate excavation volumes helps contractors estimate machinery time, organise trucks, calculate disposal costs and prepare more accurate quotes.

But how do you work out how many cubic metres of soil need to be excavated?

And just as importantly, how do you calculate how many truckloads will be required to remove it?

The good news is that for straightforward excavation work, the basic calculation is relatively simple.

What Is a Cubic Metre of Soil?

In earthmoving, excavation volumes are generally measured in cubic metres, written as m³.

One cubic metre represents a space measuring one metre long, one metre wide and one metre deep.

For example, a hole measuring:

  • 1 metre long
  • 1 metre wide
  • 1 metre deep

Contains one cubic metre of material.

If you double the length to two metres, the volume increases to two cubic metres.

Understanding this basic measurement is the starting point for calculating excavation quantities.

How Do You Calculate Excavation Volume?

For a rectangular excavation with a consistent depth, the calculation is:

Length × Width × Depth = Cubic Metres (m³)

All measurements need to be in metres.

Example: Excavating a House Site

Let’s say you’re excavating an area that measures:

  • Length: 20 metres
  • Width: 10 metres
  • Depth: 0.5 metres

The calculation is:

20 × 10 × 0.5 = 100 m³

This means approximately 100 cubic metres of soil needs to be excavated from its original position in the ground.

It’s important to understand that this is the in-ground volume, often referred to as bank volume.

The amount of space that soil occupies after excavation can be quite different.

What Happens When Soil Is Excavated?

One of the most commonly overlooked factors when estimating earthworks is something called soil bulking, sometimes referred to as swell.

When soil is sitting naturally in the ground, it has been consolidated over time.

Once excavated, the material becomes disturbed and loosened.

Air spaces develop between the particles, causing the soil to occupy more space than it originally did.

This means that 100 cubic metres of soil in the ground might occupy considerably more space once excavated and loaded onto trucks.

The amount of expansion depends on the material being excavated, its moisture content and other characteristics.

Understanding Soil Bulking Factors

For preliminary estimates, some commonly used indicative bulking allowances include:

MaterialExample Bulking Allowance
Sand10–15%
Topsoil20–30%
Clay25–40%
Broken rock30–60% or more

These are broad estimating examples, not guaranteed factors. Actual bulking varies considerably and should be confirmed using relevant material information or project-specific testing where accuracy is important.

Example: Allowing for Bulking

Using our previous excavation example:

In-ground excavation volume: 100 m³

Let’s assume the material has an estimated bulking allowance of 25%.

The calculation becomes:

100 × 1.25 = 125 m³

That means the 100 cubic metres of soil originally measured in the ground could occupy approximately 125 cubic metres after excavation.

This is important when calculating truck movements, stockpile space and material disposal.

How Many Truckloads of Soil Will You Need to Remove?

Once you’ve estimated the loose volume of excavated material, you can work out approximately how many truckloads will be required.

The calculation is:

Loose Soil Volume ÷ Usable Truck Capacity = Number of Loads

Let’s use our previous example.

  • Estimated loose soil volume: 125 m³
  • Assumed usable truck capacity: 10 m³

125 ÷ 10 = 12.5

You would therefore need approximately 13 truckloads, rounding up to the next whole load.

However, there is something important to remember.

Truck Capacity Isn’t Just About Cubic Metres

Trucks have legal weight limits as well as physical carrying capacities.

Wet clay, dense soil and rock can be considerably heavier than dry, loose material.

A truck might physically have enough space to carry a certain volume but reach its legal weight limit before the body is full.

This means that the actual number of loads may be higher than your volume calculation suggests.

Always confirm usable capacity, material weight and applicable vehicle mass limits with the haulage contractor.

How Do You Calculate the Volume of a Trench?

The same basic calculation applies to straightforward trenches with reasonably consistent dimensions.

For example, let’s say you’re excavating a trench measuring:

  • Length: 50 metres
  • Width: 0.6 metres
  • Depth: 1.2 metres

The calculation is:

50 × 0.6 × 1.2 = 36 m³

This gives you an estimated in-ground excavation volume of 36 cubic metres.

If you allow 25% for soil bulking:

36 × 1.25 = 45 m³

The excavated material could occupy approximately 45 cubic metres once loosened.

Remember that trench dimensions may need to be increased to account for safe working space, shoring or other excavation requirements.

Don’t assume the width of a trench is determined only by the size of the pipe being installed.

What if the Ground Isn’t Level?

Not every excavation has a consistent depth.

If you’re cutting a building pad into a sloping block, one side might require considerably more excavation than the other.

For simple slopes and relatively uniform ground, you can sometimes estimate the volume using an average excavation depth.

Example: Excavating a Sloping Site

Suppose an area measures:

  • Length: 20 metres
  • Width: 10 metres
  • Excavation depth at one end: 0.2 metres
  • Excavation depth at the other end: 1.0 metre

If the ground slopes uniformly and the excavation depth changes approximately linearly, the average depth would be:

(0.2 + 1.0) ÷ 2 = 0.6 metres

The estimated volume would be:

20 × 10 × 0.6 = 120 m³

This method provides a basic estimate for a simple, regular slope.

However, it isn’t suitable for every site.

Irregular ground, changing levels, retaining walls, batters and complex cut-and-fill requirements can require more detailed calculations.

For larger earthworks projects, survey information and digital terrain models are generally used to calculate volumes more accurately.

What About Batters and Sloping Excavation Sides?

Another factor that can significantly change excavation quantities is the shape of the excavation.

A pit with vertical sides has a different volume from one with battered or sloping sides.

For example, an excavation with a 10-metre by 5-metre base may need a much larger opening at ground level if the sides are battered.

The additional material removed can be substantial.

The required batter slope depends on ground conditions, excavation depth, surrounding loads and the excavation design.

For safety-critical excavations, suitable battering, benching or shoring arrangements should be determined by a competent person and, where necessary, an engineer.

Don’t calculate excavation quantities using only the finished base dimensions if the excavation requires wider sides or additional working space.

What Is Cut and Fill?

On larger earthmoving projects, contractors often need to calculate both cut and fill quantities.

Cut refers to material that needs to be excavated.

Fill refers to material that needs to be placed to raise or level part of a site.

For example, a sloping property might require soil to be removed from the higher section and placed in the lower section.

Ideally, some or all of the excavated material can be reused on-site, reducing the need for imported fill or off-site disposal.

However, cut and fill volumes can’t always be compared directly.

Soil changes volume when excavated and compacted, and not every material is suitable for use as structural fill.

Moisture content, compaction requirements and material suitability all need to be considered.

For larger projects, a proper earthworks balance can help determine how much material can be reused and how much needs to be imported or removed.

How Accurate Are Excavation Volume Calculations?

A basic length-by-width-by-depth calculation is useful for preliminary estimating, but it has limitations.

Actual excavation quantities may change because of:

  • Uneven or sloping ground.
  • Variations in excavation depth.
  • Over-excavation and working allowances.
  • Batters and benching.
  • Rock or unsuitable material.
  • Soil bulking and compaction.
  • Differences between design and actual site levels.

For small, straightforward jobs, basic measurements may provide a reasonable starting point.

For larger civil works, bulk earthworks or complex excavations, survey measurements, engineering drawings and digital earthworks calculations can provide more reliable quantities.

Why Getting Excavation Quantities Right Matters

For earthmoving contractors, underestimating excavation volumes can affect the profitability of a job.

An incorrect calculation can mean:

  • More machinery hours than allowed for.
  • Additional truck movements.
  • Higher disposal charges.
  • Extra labour and fuel costs.
  • Project delays.
  • Reduced profit margins.

If you’re quoting a fixed-price job, these additional costs may become your responsibility unless the contract allows for a variation.

Accurate quantity calculations are an important part of preparing realistic earthmoving quotes.

Take the Guesswork Out of Excavation Volumes and Truckloads

Working out how much material needs to be excavated is one thing, but estimating how many truckloads you’ll need to remove it is just as important.

Getting these calculations wrong can lead to additional truck movements, unexpected disposal costs, project delays and reduced profit margins.

The Earthworks Hub Volume and Truck Load Estimator helps contractors calculate excavation volumes, allow for soil bulking and estimate the number of truckloads required to remove material.

Whether you’re preparing a quote, organising trucks or planning an excavation, having a reliable estimate can help you make better decisions before work begins.

Stop guessing your excavation quantities. Know your volumes and plan your truckloads before starting the job.

Calculate Your Excavation Volume & Truckloads

The Bottom Line

Calculating excavation volumes doesn’t need to be complicated for straightforward jobs.

Start with the basic formula:

Length × Width × Depth = Cubic Metres

Then consider soil bulking, the actual excavation shape, truck capacity and any material that needs to be reused or disposed of.

For more complex sites, use appropriate survey or engineering information rather than relying on rough measurements.

And remember, knowing how many cubic metres need to be excavated is only the beginning.

Understanding the volume of material, the number of truckloads required and the costs involved is what helps turn an accurate quantity estimate into a profitable job.

Earthworks Hub — Connecting Australia’s Earthmoving Industry


Disclaimer: The examples and bulking factors in this article are indicative only. Actual excavation quantities, material characteristics and truck capacities vary. Complex excavation designs and safety-critical work should be assessed by suitably qualified professionals.